Village Approves Infrastructure Repairs, Updates Gateway Subdivision

DAVIS JUNCTION – Trustees approved a $42,230 bid from Martin & Co. for Junction Road shoulder repairs and reviewed ongoing inspections in Harvest Glenn Subdivision Plat 10 Tuesday night, with all ditches and culverts meeting grade requirements. Updates on the Gateway Subdivision show detention ponds and swales shaped, erosion controls installed, and concrete footings and foundation walls poured for Lot 1, with the project slated for completion by June 30, 2026.